M/s Mega Engineering Infrastructures Ltd. Hyderabad
170MLD Water Treatment Plant at Maripeda (Warangal Dist)
- 30,000 KL Sump (Biggest in TSWG Work) Structure completed, finishing works in progress
In Sump 75,000 Cum Blasting is done in 60 Days.
- WTP 170 MLD
Aerator -Completed
Chemical House – Completed
Chlorination – Completed
Clariflocculator 1, 2 & 3 (57M dia) – Completed
Filter House with 16 Beds (Completed)
E&M works in Progress
23MLD Water Treatment Plant at Kaddam (Adhilabad dist)
- Intake wall at kaddam reservoir from 17.5M below MFL is completed up to Floor slab in jest 3Months (incl. Coffer dam, Dewatering etc )
- Bridge of 85M Length is Completed –in Just 45 Days
- As we said we work with a proper planning it was best example. Since our intake area will be submerged in the month of June we have planned our project accordingly we have completed the risk part. Now balance 23MLD WTP area are in finishing stage
- December we are planning for trail run
M/s. Swathi Promoters Pvt.Ltd
- 45acrs Layout development works at RJY in Progress
- 24.5acrs Layout development works at RJY in Progress